November 12, 2026
"I'm chomping at the bit like a horse at a race," restaurateur Brian Piccini told the Weston Observer in October. He was talking about The Woods, the restaurant he plans to open inside the town-owned Josiah Smith Tavern. In August we described the project as waiting on 22 parking spaces. Those spaces have since been approved.
The project's remaining questions now sit with the Select Board in its role as landlord. Both sides say they want a restaurant in the Tavern. They disagree about order: when $1 million goes into escrow, who confirms construction spending, and when the free-rent period begins.
On Sept. 30, 2026, the Weston Zoning Board of Appeals approved Boston Urban Hospitality's variance for 22 additional on-street parking spaces, according to an Oct. 8 update from the Friends of Josiah Smith Tavern. Here is how the bylaw's 77-space requirement now adds up:
The Friends are the nonprofit that holds the master lease and subleases the building to Piccini's company, BUWest. They list approvals from Historic New England, the Planning Board, the Historic Commission, the Permanent Building Committee and now the ZBA. They also say BUWest has completed its construction documents, chosen a contractor and put more than $455,000 of Piccini's own money into the project. Piccini is a Weston resident. That puts BUWest, in the Friends' words, "ready to apply for a building permit."
The permit can't come until the sublease is amended, and that amendment is the part still unsettled.
The Select Board sent its terms in a letter dated Oct. 8, a week after the parking vote. The Weston Observer reported that the Board considers the Friends and Piccini in breach of the master lease. Its reasoning is that the restaurant has not opened and no rent has been paid even though a year has passed since the liquor license was issued. The original lease, signed in March 2024, required rent to start one year after the liquor license, which was also issued that month.
The letter set an Oct. 15 deadline to sign. Otherwise, the Board said, it might enforce the existing agreement, including seeking money owed and ending the lease. Chair John McDonald told the Observer the Board is prepared to step away from The Woods but believes an agreement is still possible.
"That is all to protect the interests of the town," McDonald said, describing the proposal as a way to make sure Piccini has the money to finish the work.
Friends president Jay Valenta told the Observer the group did not sign. It sent back a list of the changes it needs before moving forward. Here are the two positions, term by term:
| Term | Oct. 8 Select Board letter | Friends and BUWest response |
|---|---|---|
| $1 million construction escrow | Funded within 30 days of signing | Piccini agreed to fund it but objects to funding before the sublease amendment is final |
| Releasing escrow money | Town building inspector confirms progress and spending | Valenta prefers a third party |
| Missed milestones | Town may seek immediate termination | A grace period for delays such as weather |
| Free rent | Up to nine months, starting when the agreement is signed | Should begin around opening, as the original business terms intended |
The rent relief in the Board's letter would come in three steps. The first three months come at signing, three more once construction begins, and the last three once the project reaches the halfway point on a schedule Piccini sets and the building inspector approves.
The Friends explain why the start date matters to them in an Oct. 17 post. The original terms gave 180 days of construction after the building permit, then nine months of free rent. The town is not paying any tenant improvement allowance toward the build-out. If the free-rent clock starts at signing, the Friends argue, most of it would be used up during permitting and construction instead of the restaurant's first months in business.
Valenta told the Observer that unexpected delays, such as weather, can happen and that the agreement should include a grace period instead of allowing the town to withdraw immediately. He described that grace period as standard. "There's no concern or fear [about not meeting milestones], but it's a typical provision that would be around the lease," he told the Observer.
The October standoff is the Board's second ultimatum of 2026. The first one went the same way and was resolved.
The July meeting also previewed the October dispute. Member Anupam Sachdev wanted incentives to keep the March date on track. Member Lise Revers cautioned that finishing the lease and escrow agreements would take more than two days. The escrow idea itself came from the Friends and BUWest in July as a way to prefund construction. Both sides now agree there should be an escrow. They still disagree about when it gets funded.
McDonald spoke to the project's history at the July meeting:
"The way to show that's not going to be the case this time is to execute and perform on that."
The history behind that remark is long. According to the Observer's October account, the Tavern's exterior rehabilitation began in 2009. A restaurant was first proposed in 2012, the Board chose the Friends to manage the project in 2016, and Piccini's bid was accepted in 2023. The Friends add that residents voted for the project in 2019.
The March 2027 opening was a July estimate. It assumed construction would begin by September. In mid-October, the Friends described BUWest as ready to apply for a building permit once the agreements are signed, which is still a step before construction. Under the original business terms, the 180-day construction period starts only after the permit is issued. No opening date holds until the agreements are signed.
Much of the negotiation is out of public view. Since the beginning of June, the Board has met six times on the Tavern in executive session, which the public cannot attend and which Piccini and the Friends have not been part of. McDonald told the Observer this is the norm. In their Oct. 17 post, the Friends asked the Board to appoint one member to negotiate directly with them and BUWest. They also listed the Select Board's email addresses and the Town Hall number, 781-687-5000, for residents who want to weigh in.
The Friends also point out that the town keeps paying to maintain the Tavern while it sits empty. Piccini, for his part, told the Observer he sees the town "trying to protect their historic asset, which I respect."
The next fixed date in the town center is the Weston Community League's Holiday Tree Lighting on Sunday, Dec. 6, at 3:45 p.m., across from the Fire Station.
A finished town center with a restaurant at its center would change what Weston Center offers on an ordinary weeknight, and homeowners nearby will reasonably wonder how that figures into their property's value. If you would like a measured read on how projects like The Woods tend to show up in Weston pricing, Jamie Grossman is glad to talk it through. Request a Personalized Home Valuation, and we'll look at your home alongside what's happening at the Tavern.
Stay up to date on the latest real estate trends.